A WMS go-live touches everyone: the floor, the office, your IT people, the software vendor and, in a 3PL, every client whose orders run through the building. On go-live day a surprise is expensive. A picker who wasn’t trained. A client who heard about the cutover from someone else. A carrier pickup nobody moved.
A communication plan is how you stop those surprises. It sets out who needs to know what, who tells them, how and how often. The same plan works when you onboard a new client.
Write it at the start of the project, as part of the project plan.
What a communication plan includes
It’s usually a two- or three-page document that covers:
- The objectives. A short paragraph on what the project, or the go-live, must achieve.
- The people involved. Their roles and responsibilities, and a little about the work each person will do.
- The wider group of stakeholders. Sponsors, managers, clients, suppliers, contractors, end users and anyone else affected. In a 3PL, your clients are on this list from day one.
- Contact details for everyone. Often kept in a separate document, so it’s easy to find.
- The types of communication. Documents, meetings, calls, presentations and formal emails.
- The communication table. Each key communication, who receives it and how often. A table is easiest to read.
- The standards everyone follows. For example, every change request goes in writing by email, never by word of mouth.
Here’s what the table might look like for a go-live:
| Communication | Who gets it | How often |
|---|---|---|
| Status report | Owner and project sponsors | Weekly |
| Readiness update | Each client | Weekly, then daily in the last two weeks |
| Floor briefing | Supervisors and leads | At the start of each shift in the last month |
| Change requests | Project lead and the vendor | In writing, as they come up |
| Cutover schedule | Everyone on the project | Updated daily during cutover |
Why it matters
Poor communication is often visible only after something has gone wrong. Two examples:
- A problem that doesn’t exist. The team passes on an issue badly, and people spend time and money chasing it. A good plan avoids that, because everyone knows who to talk to, and when and how information moves from person to person.
- A client who hears it from someone else. If a client learns about the go-live date, or a delay, from anyone but you, the relationship takes the hit. Send status updates straight to each client every week, so they never have to piece it together.
A communication plan puts the project manager in charge of who hears what, and when.
Tips for writing one
- Match the method to the audience. A senior manager wants something quick to review: a short report, or a brief presentation with time for questions. Don’t add to their emails and phone calls.
- Keep the wider group informed. A regular email update tells end users what’s happening and how it affects their work. On the floor, a word at the start-of-shift huddle reaches people email doesn’t.
- Meet the project team in person. Regular face-to-face meetings let everyone raise concerns and work through issues. Keep them short with a daily stand-up of 15 minutes or less.
- Use email sparingly. It’s easy, but tone and context are hard to get across in writing.
- Make sure everyone has read the plan. It works only if people follow it.
- Keep one copy of everything. Put reports and records in one shared document library, so nobody works from an old version.
The takeaway
It’s tempting to spend all the planning time on dates, people and budget. Communication is easy to forget, yet it keeps everyone working toward the same objectives with the same information. Set aside time at the start to write the plan. It might be the one thing that helps your go-live succeed.